Posted on May 1, 2017 at 8:02 AM by Communications Department
** UPDATE - This work, originally scheduled for Saturday, May 20 from 6 a.m. to 6 p.m. will now begin at midnight on Friday, May 19 and continue until 6 p.m. Saturday, May 20.
Sanitary Sewer Pipeline Installation

HRSD is scheduled to install sanitary sewer pipelines across Warwick Boulevard between Abbitt Lane and the Peninsula Memorial Park entrance Saturday, May 6 and the following Saturday, May 13, from 6:00 a.m. to 6:00 p.m. Motorists should be prepared for reduced speeds and temporary lane shifts during this time.
A temporary lane shift will divert all southbound traffic

to the median side of Warwick Boulevard’s northbound lane, continuing down the median side of the northbound lane and merging back into the southbound lanes of Warwick Boulevard near the Peninsula Memorial Park entrance. The speed limit in this area will be reduced to 35 MPH during construction.
This work is part of the
Warwick Boulevard Force Main Replacement - Scufflefield Road to Peninsula Memorial Park project.